campus facilities wmu seal top
western michigan university home page wmu directories wmu contact page
wmu seal bottom
Chemistry Building
View of looking west from the University Computing Center
curve curve
Chemistry Building West Elevation
curve

Site Control Plan
 
Pedestrian Traffic
 
 

East Elevation
Pedestrian Traffic Signs
Click to enlarge


Auditorium
Project Schedule
Click to enlarge

Third Floor Cooridor
Project Schedule
Click to enlarge

Lab Casework
Project Schedule
Click to enlarge
 

Lecture Hall
Project Schedule
Click to enlarge
 


September 2006

Construction began in the Spring of 2005 on the new Chemistry Building. Currently, the building exterior is 90% complete. The mechanical and plumbing is 98% complete Metal studs, drywall, and interior masonry walls have been installed on all floors. Laboratory casework is scheduled for installation in the month of September. The Miller Plaza Promenade is completed as well, along the west side of the new Chemistry Building.

The building completion is slated for October of 2006, with classes to be held in the building January 2007. The building dedication is scheduled for December, 2006.

 

 

 

 

 

 

 

Top


Copyright © Western Michigan University, All Rights Reserved
Last Revised: March 31, 2008