Oliver Street Reconfiguration

Road Opening ROAD  OPENING  FRIDAY,  AUGUST  29

Oliver Street is open for traffic as of Friday, August 29. 

May Construction Photos

July Construction Photos

August Construction Photos

 

PROJECT  SUMMARY:
With the help of a grant from the State of Michigan, the university reconfigured Oliver Street, the campus road that runs between Stadium and Oakland Drives.

The project took place in three stages over the summer of 2008 and was completed in August, in time for the start of fall semester.

The total scope of the project included a new roadway and sidewalks, bicycle paths, and reconstructed parking lots.

Also included in the project was a stormwater management plan to prevent building and parking lot run-off from entering the Arcadia Creek watershed.


Existing roads configuration and construction sequence. Click to enlarge.

 

Map of future campus roads after construction is complete. Click to enlarge

 